I-80 Across the Top Bus/Carpool and Auxiliary Lane

Description: In Sacramento within the median of I-80 from the Sacramento River Bridge to Watt Avenue. Construct Bus/Carpool (HOV) lanes, auxiliary lanes, retaining walls, soundwalls and TOS elements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95864
 
Senate District
06
Assembly District 05, 09
Congressional District 05
 
Caltrans District
03
 
 
County/State Route Sacramento 80
Postmile Begin/End 0 10.1
 
County/State Route Sacramento 80
Postmile Begin/End 0 10.1
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  8,425      
Lane Miles Added (HOV)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Winder Bajwa (530)741-4432   Winder_Bajwa@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Jess Avila (530)741-4533   Jess_Avila@dot.ca.gov
Right of Way Phase
Department of Transportation Jess Avila (530)741-4533   Jess_Avila@dot.ca.gov
Construction Phase
Department of Transportation Jess Avila (530) 741-4533   Jess_Avila@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Marlon Flournoy (530) 741-4337   marlon.flournoy@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$65,000 $-11,463 $53,537
Non-bond Funding
State/Federal*
$0 $72,998 $72,998
Local**
$9,500 $0 $9,500
 
Total**** $74,500 $61,535 $136,035

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$2,700 $0 $2,700 $2,324
Design(PS&E)
$5,000 $2,911 $7,911 $8,273
Right of Way
$1,800 $36 $1,836 $904
Construction
$65,000 $58,588 $123,588 $136,324
 
Total* $74,500 $61,535 $136,035 $137,825

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/15/2005 

02/11/2008 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/15/2008 

10/01/2010 
 

 
 

09/08/2010 
100   

09/08/2010 


Begin Right of Way Phase

End Right of Way Phase
02/01/2008 

10/01/2010 
 

 
 

 
98   

 


Begin Construction Phase

End Construction Phase
03/01/2011 

11/01/2014 
 

 
07/29/2011 

12/30/2016 
07/29/2011 

12/30/2016 


Begin Closeout Phase

End Closeout Phase
11/01/2014 

11/01/2016 
 

 
01/16/2017 

11/01/2018 
11/15/2016 

07/30/2023 


-58 
Corridor System Management Plan
Adoption Date 06/01/2010    06/01/2010   
Implementation Date 06/01/2010    06/01/2010   
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 8,425
Lane Miles Added (HOV) 20

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.