I-80 Across the Top Bus/Carpool and Auxiliary Lane |
Description: In Sacramento within the median of I-80 from the Sacramento River Bridge to Watt Avenue. Construct Bus/Carpool (HOV) lanes, auxiliary lanes, retaining walls, soundwalls and TOS elements.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | 95864 |
Senate District |
06 |
Assembly District | 05, 09 |
Congressional District | 05 |
Caltrans District |
03 |
County/State Route | Sacramento 80 |
Postmile Begin/End | 0 10.1 |
County/State Route | Sacramento 80 |
Postmile Begin/End | 0 10.1 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 8,425 | |
Lane Miles Added (HOV) | 20 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Winder Bajwa | (530)741-4432 | Winder_Bajwa@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Jess Avila | (530)741-4533 | Jess_Avila@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Jess Avila | (530)741-4533 | Jess_Avila@dot.ca.gov | |
Construction Phase |
Department of Transportation | Jess Avila | (530) 741-4533 | Jess_Avila@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Marlon Flournoy | (530) 741-4337 | marlon.flournoy@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
CMIA |
$65,000 | $-11,463 | $53,537 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $72,998 | $72,998 | ||||
Local** |
$9,500 | $0 | $9,500 | ||||
Total**** | $74,500 | $61,535 | $136,035 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$2,700 | $0 | $2,700 | $2,324 | |||
Design(PS&E) |
$5,000 | $2,911 | $7,911 | $8,273 | |||
Right of Way |
$1,800 | $36 | $1,836 | $904 | |||
Construction |
$65,000 | $58,588 | $123,588 | $136,324 | |||
Total* | $74,500 | $61,535 | $136,035 | $137,825 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
09/15/2005 02/11/2008 |
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/15/2008 10/01/2010 |
|
09/08/2010 |
100 | 09/08/2010 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
02/01/2008 10/01/2010 |
|
|
98 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
03/01/2011 11/01/2014 |
|
07/29/2011 12/30/2016 |
0 | 07/29/2011 12/30/2016 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2014 11/01/2016 |
|
01/16/2017 11/01/2018 |
0 | 11/15/2016 07/30/2023 |
2 -58 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2010 | 06/01/2010 | 0 | 0 | |||
Implementation Date | 06/01/2010 | 06/01/2010 | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 8,425 | |
Lane Miles Added (HOV) | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.